A society should size storage from its common-area loads and outage records, then compare the installed cost with a documented operating-cost baseline. Payback, uptime and a reduction in residents' charges depend on the project; they are not fixed benefits of buying a battery.
Start with measured loads
Collect electricity bills, interval demand data, diesel purchase records, generator running hours and the loads that must remain available. Separate lifts, pumps, lighting, security and other critical services. Check motor starting demand, fire access, structural capacity, electrical protection and the battery recharge window with the engineering team.
Power in kW determines how much load the system can supply. Energy in kWh determines how long it can supply that load, after allowing for reserve capacity and system losses. A power rating alone cannot establish backup hours.
An illustrative budget calculation
The following figures are hypothetical inputs, not a TOBOR quotation or customer result:
| Input | Example |
|---|---|
| Installed project cost | ₹70 lakh |
| Current annual operating cost | ₹18 lakh |
| Proposed annual operating cost | ₹8 lakh |
| Annual operating saving | ₹10 lakh |
| Simple payback | 7 years |
Simple payback is ₹70 lakh ÷ ₹10 lakh/year. For 100 households, ₹10 lakh/year equals approximately ₹833 per household per month before financing, reserve contributions and other society costs. It is not a promised reduction in charges. Include maintenance, battery degradation, future replacement, insurance, financing and taxes in the full cash-flow model. Do not count capital repayment as both an operating expense and an upfront investment.
Prepare the society's decision
Obtain a technical design, an itemised offer, maintenance terms and a realistic commissioning schedule. Follow the society's applicable governance process for approvals. Record the critical-load scope, responsibilities, warranties and service arrangements in the proposal. Do not assume a universal voting threshold, completion timeline or subsidy entitlement.
Solar incentives and funding
Assess solar assistance separately from battery cost. Check the current scheme and applicant category before including incentives in the budget. Loan rates, collateral, tenure and repayment terms require a lender's offer. Compare annual cash savings with actual annual debt payments.